The Constructing Excellence Innovation in Practice project ‘Hammersmith Flyover (Phase 2)’ Design Stage case study is now available to download

The Hammersmith Flyover was constructed in the early 1960’s and is situated in West London. In December 2011, the post tensioning tendons that run through the structure were found to have been deteriorating at a significant rate, and in December 2011 the Hammersmith flyover was closed under emergency conditions. The first ‘initial strengthening’ phase of works were completed in summer 2012 prior to the Queen’s Jubilee weekend and the London 2012 Games.

Phase 2 (and final phase) of the works programme to refurbish and strengthen the remaining spans of the bridge commenced in April 2013 and is planned to be complete in summer 2015.

A case study giving full details on the design stage of the project is available to download here. CE Hammersmith Bridge Final Case Study